Efficiency em LinkedIn+ Twitter Facebook 07538823112

Case Study: Kitchen Upgrades

May 9th, 2018 by

Kitchen Upgrades at the Patchills Centre

Client Brunts Charity
Contractor  Matthews & Tannert
Manufacturer  Rixonway Kitchens
Framework   EEM0057 – Kitchen and Bathroom Installations
Contract   JCT Measured Term 2016
Programme  Sep-Dec 2017 – 12 weeks
Value   £102,500


 

Introduction
The Patchills Centre is owned and managed by Brunts Charity and provides sheltered accomodation to the elderly in the form of 158 properties (25 flats and 133 bungalows).
It benefits from a large community centre from where site wardens are based that runs fitness classes, bingo and a lunch club.
The 17 year old kitchens within the flats were in desperate need of an upgrade.


Procurement
Brunts Charity approached EEM to assist with the procurement of a contractor to undertake these works. Matthews & Tannert were selected from the EEM framework for the installation of kitchens and bathrooms due to their locality and the suitability of works.
Rixonway Kitchens were selected to provide the units due to them being EEM’s compliantly procured manufacturer.


The Project
A total of 23 flats and a bungalow required kitchen upgrades within The Patchills complex.

Works Undertaken

Preparation
The kitchens were emptied of white goods and cooking appliances and re-connected elsewhere for use where possible. All existing kitchen units, worktops, sink, tiling and other wall coverings, flooring, skirting boards were stripped out. Walls received new plaster skim and new curtain battens were fitted.

Kitchen Installation
Rixonway kitchen units (Trieste Range) were installed (up to 8 units per kitchen) with soft close drawers. New kitchen work tops and supports were installed to pre-determined specifications. New sinks were installed as well as uPVC window cill board and new cooker restraint chains.

Floor Covering & Decoration
New vinyl flooring was fitted, as selected from the range by the tenant. Walls, ceilings & woodwork were decorated with two coats of emulsion paint, as selected by the tenant.

Electric Wiring

The kitchens were re-wired and tested upon completion with certificates issued.


Challenges

The flats were occupied by elderly tenants who required minimal disruption.
Communication was key, so all tenants were briefed in advance so they knew what to expect.
As the flats are occupied, white goods and other items were re-connected in the living rooms and other locations so they could still be utilised. Tenants were also able to access the communal kitchen area.
A quick turnaround was required to minimise disruption so a timeline of 7-10 days per 4-6 kitchens was established. Although there was a slight delay in some of the materials being delivered, Matthews & Tannert managed to work around the issues and still complete the project on time.
A co-ordination schedule was set up to allow skimmers, plasterers, electricians, kitchen fitters, tilers, flooring fitters and decorators to complete their works as efficiently as possible.
Certains works were sub-contracted so quality control needed to be closely monitored. Brunts Charity were pleased to see any issues were addressed and corrected promptly by Matthews & Tannert.


 

Results

The kitchens were successfully completed within the timeframe, before the busy Christmas period.
Brunts Charity consider this to be an investment into the well-being of the residents as well as the infrastructure of the complex. They recognise the positive impact these works have had on the morale and social well being of the tenants.
Brunts had not previously worked with Matthews & Tannert but following this successful project, more works have been awarded to the local contractor.


 

Feedback

“With a considerable investment, Brunts charity completely upgraded 23 flat kitchens and 1 bungalow taking into account the specific needs of our elderly resident, who were living on-site during renovation. It was imperative that the Patchills site project could bring together successful stakeholder engagement in order to achieve successful outcomes within a tight time-frame of three months.
“EEM Project Officer, Louisa Payne, ensured we were linked into a professional network of contractors and suppliers and the outcome was a project delivered to our complete satisfaction, with all expectations met.”
Paul Williams – Operations Manager, Brunts Charity

“Further to the pre start meeting with Brunts and Matthews & Tannert (M&T) Rixonway commenced and completed all surveys within 26 days.  M&T placed their call off order and deliveries were made on time throughout November/December.   The work  went very  well,  and  working  with  Matthews & Tannert ensured that the programme not only met but exceeded both the clients and residents expectations.
“Following the completion of the flats, as a demonstration of our support to the communities that we work within, Rixonway donated a kitchen to the communal area. The Trieste mid gloss kitchen with beech worktops and tapered D handles reflected the residents own kitchens.”
Kath Almond – Sales Development Manager, Rixonway Kitchens


BeforeAfter

 

Connect with Us